Timeline of Konterra Pollution Events
December 19, 2007
AWS detects severe sediment pollution in the waters of
Northeast Branch, a major tributary of the Anacostia River.
Seeking an explanation for the increased turbidity, AWS
experts work their way north and east along Northeast
Branch and Indian Creek to find the source of the problem (see Photo 1).
The search leads to Konterra Subdivision and the
sand mining operation run by Laurel Sand & Gravel. AWS
personnel note the discharge of an excessive amount of
turbid water from the site. The pollution event is reported
to MDE and the Prince George’s County Department of
Environmental Resources (PGDER).
AWS personnel researched rainfall amounts in the Washington, D.C. metropolitan area on December 19 and each of the 5 days prior to their discovery. Table 1 gives the total amount of rainfall measured at Reagan National Airport on each day. Accordingly, it was determined that Indian Creek remained extremely turbid 3 days following the last appreciable rain.
| Table 1. |
Date |
Precipitation
at Reagan National Airport (in inches) |
Dec. 14 |
0.00 |
Dec. 15 |
0.15 |
Dec. 16 |
0.72 |
Dec. 17 |
0.00 |
Dec. 18 |
0.00 |
Dec. 19 |
0.00 |
December 27, 2007
PGDER concludes a preliminary investigation of Konterra
Subdivision and issues a violation (#12-01-004) to the
site’s stormwater permit holder, 1325 G Street Associate,
LLLP. Under the terms of the violation, the permit holder
is ordered to mitigate the existing pollution and prevent
additional sediments from entering Indian Creek. In their
report, PGDER inspectors note that supervision and enforcement
for stormwater control policies at Konterra
Subdivision fall under the jurisdiction of MDE’s Minerals,
Oils, and Gas Division. The violation is forwarded to that
agency pending further action.
January 15, 2007
PGDER re-inspects Konterra Subdivision and concludes
that “sediment and erosion devices installed [were secured]
per plans and specifi cation” [1]. The inspector emphasizes
that re-inspection occurred immediately following
a rainfall event.
AWS personnel research rainfall amounts in the Washington, D.C. metropolitan area on January 15 & 16 and each of the 5 days prior to the PGDER re-inspection. Table 2 gives the total amount of rainfall measured at Reagan National Airport on each day. Comparison with total rainfall amounts and timeframes researched during December 2007 (see above) and later in Febrary 2008 (see below) suggests that percipitation volume on and around January 15 was not significant enough to overwhelm stormwater control devices installed at Konterra Subdivision.
| Table 2. |
Date |
Precipitation at Reagan National Airport (in inches) |
Jan. 10 |
0.18 |
Jan. 11 |
0.15 |
Jan. 12 |
0.0 |
Jan. 13 |
0.03 |
Jan. 14 |
Trace (<0.1) |
Jan. 15 |
Trace (<0.1) |
Jan. 16 |
0.0 |
January 24, 2008
MDE inspectors complete their own investigation of Konterra
Subdivision. In their report they describe a site undergoing
“massive restoration and reclamation” [2]. While the same report acknowledges that a portion of silt fence
around a stormwater retention pond has failed, it records
that the site has been maintained without major problems.
The inspectors support this claim by noting additional
stormwater controls throughout the site that appear to be
functioning. Controls specifically mentioned include vegetative stabilization, silt bagging, and ongoing construction
at a permanent (though non-functional) stormwater
management structure.
February 1, 2008
The Washington, D.C. metropolitan area experiences a
relatively heavy rainfall event. Precipitation reaches 2.05
inches. With the threshold for a one-year-storm event in Prince George’s County set at 2.7 inches of rain, this
means that an event like the one on Feb. 1 could occur
more than once a year.
February 3, 2008
Two days following the storm on Feb. 1, AWS experts note
that water in Indian Creek is excessively turbid. AWS personnel
track the source of turbidity back to the sand mining
operation at Konterra Subdivision. Seeking to compare
the condition of Indian Creek with conditions on other
Anacostia tributaries, AWS travels to nearby Little Paint
Branch. The stream comparison leads to photographic
evidence of pollution on Indian Creek due to excessive
turbidity (see Figure 1).
Figure 1. Photographic Comparison of Turbidity Levels on Indian Creek and Paint Branch Two Days Following a 2.05" Rainfall Event on February 1, 2008. |
|
|
February 4, 2008
AWS returns to Indian Creek to confirm that sediment runoff
from Konterra Subdivision continues to pose a threat.
AWS personnel report to PGDER and MDE what they now
consider an ongoing sediment problem at Konterra Subdivision.
PGDER inspectors arrive the same day to investigate
the new complaint. They determine that sediment
capture devices at Konterra—including a silt bag, a stone
retaining wall, and several silt fences—have failed to cope
with the rainfall delivered by the latest storm (see Photo 5).
February 5, 2008
MDE inspectors visiting Konterra Subdivision confirm the
failures noted by PGDER the previous day. The inspectors
send notice to the site permit holder indicating that
upgrades to all failed stormwater control devices must be
undertaken immediately. They recommend that all silt
fences on the property be replaced with supersilt fences,
and that the toppled retaining wall be rebuilt using a trackhoe
machine. Inspectors also announce their intention to
discuss application of additional stormwater control measures at Konterra, including the use of a flocculent (i.e., a
material that will cause sediment suspended in stormwater
to aggregate and fall out of solution). Note: The MDE
site report from Feb. 5 specifically notes that all control
structures listed as failed had appeared on the schedule
of sediment and erosion plans approved by MDE and the Prince George’s Soil Conservation District [3].
February 6, 2008
An AWS investigation reveals that excessively turbid water
from Konterra Subdivision continues to pollute Indian
Creek.
February 12-13, 2008
Rain falls in the metropolitan region once again. Precipitation
amounts measure 0.18 inches on the 12th and
1.17 inches on the 13th.
February 15, 2008
Once again, AWS reports excessive turbidity on Indian
Creek emanating from Konterra Subdivision. Once again,
natural turbidity levels on nearby Little Paint Branch are
recorded for comparison (see Figure 10). MDE inspectors
announce plans to visit Konterra the following week.
They note that gypsum may soon be used onsite as a flocculent.
Click here for video footage of sediment-polluted water from Indian Creek mixing with cleaner water from Little Paint Branch. (Filmed: February 15, 2008.)